PI001 | Actual drydocking costs V4.0

Performance Indicator

This PI captures ship’s actual drydocking costs.


Definition

The total actual costs associated with the drydocking. This shall include in-water survey (IWS), modifications and repairs, not included in routine running costs. It also includes costs for any additional work not planned for before the drydocking.

UnitUSD
ScopeReported on a ship level
Calculation periodCaptured and reported in the quarter the drydocking was completed
ReferencesThis Performance Indicator - PI001 - is used by the following Key Performance Indicators
KPI010Drydocking planning performance
PI001Actual drydocking costs
PI002Actual drydocking duration
PI004Agreed drydocking budget
PI005Agreed drydocking duration
Example

Actual drydocking cost in US$ = 3,920,800